Installation process of thin film evaporator
May 16, 2023
Leave a message
film evaporator installation
1. The thin film evaporator has been tested as a whole before leaving the factory, and the user can hoist the whole equipment to the equipment foundation.
2. The equipment should be leveled as a whole, and the leveling position can refer to the plane on the reducer frame. And fix the equipment on the floor or on the steel frame.
3. For equipment with larger specifications, in order to increase the stability of the equipment, an auxiliary support in the horizontal direction can be added to the appropriate part of the upper part of the bottom flange. The auxiliary fulcrum only limits the radial displacement of the equipment, not the axial displacement.
4. Prepare the pipeline according to the process requirements, remove foreign matter, clean and replace the equipment, and connect the power supply.